1.-M. ID 22-1474 Actions pertaining to the South Peach Avenue Park Phase 1 Project (Council District 5):
1. Affirm the City Manager's finding that Blair, Church & Flynn Consulting Engineers, Inc., is uniquely qualified: and
2. Approve a Consultant Services Agreement with Blair, Church & Flynn Consulting Engineers Inc., in the amount of $626,000, with a contingency amount not to exceed $60,000, for the design and preparation of construction documents for the South Peach Avenue Park Phase 1 Project
3. Authorize the Public Works Director or designee to execute the contract and amendments approved by the City Attorney's Office on behalf of the City of Fresno