Meeting Time: February 26, 2026 at 9:00am PST
The online Comment window has expired

Agenda Item

2.-F. ID 26-197 Actions pertaining to the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport (Council District 4),Bid file 12502600: 1. ***RESOLUTION - Adopt the 38th Amendment to the Annual Appropriation Resolution (AAR) No. 2025-179 appropriating $7,500,000 for the AIP 106 Reconstruction Runway Project 11L-29R for Fiscal Year 2025-2026 (Requires 5 affirmative votes) (Subject to Mayor's veto). 2. Award a Construction Contract to A. DeSilva Gates Construction-Vanguard A Joint Venture, of Dublin, California, for the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport in the amount of $98,888,888.00 (Bid File 12502600), with a notice to proceed each year contingent on FAA funding. 3. Approve a Consultant Agreement with Krazan of Fresno, California, to provide geotechnical quality assurance testing and inspection services for the Runway 11L-29R Reconstruction project at Fresno Yosemite International Airport in the amount of $1,164,070.00 for a term of three (3) years, with a notice to proceed each year contingent on FAA funding 4. Approve a Consultant Agreement with Kimley Horn for professional construction management and phasing services in the amount of $4,391,389.00 for a term of three (3) years, with a notice to proceed each year contingent on FAA funding